Club Extension 2010


1) Demolishing the old storage shed. 
This was the first stage of the process, undertaken by several volunteers on the Working Party day in March 2010.


                               

 


2) Laying the foundations.

Next came several hours of digging in preparation for the laying of the foundations for the new building. Thanks to Dave P, Dave O and especially to Keith and Brian for the additional hours they spent on this.

                             



3) Installing the cesspool.

The cesspool tank was kindly donated by Klargester. Thanks to Ches for organising this.    


                        




4) The finished building

                                    




The Happy Plumbers, Ches and Keith!

            

                